The one thing that goes wrong at acceptance is checking static accuracy without checking motion. The correct order is level, air and hydraulics, dry run, tool setting, test cut, records. Skip one step and you repeat it later.

In the first days after delivery the shop floor rarely asks about price; it asks what to do first. These ten questions follow the real sequence from unloading to a stable first part.
Where a figure is quoted, it comes from the product table on this site; where the table is silent, the answer says so.
Leveling, and level it on free supports. Set the machine on its pads, measure with a precision level at both ends and the middle of the bed, and adjust each pad until both longitudinal and cross readings are within tolerance, then lock. Running the machine before leveling means every later accuracy check drifts.
Air: check supply pressure stability and the pressure drop during turret and chuck action. Hydraulics: oil level, oil temperature and clamping pressure gauge. On machines with a sub-spindle, such as HMS-550MYS, also confirm sub-spindle clamp and unclamp travel; both sides must be fully clamped before the two spindles meet.
Inch before continuous. Run the spindle at low speed forward and reverse, index the turret manually, jog X, Y and Z one at a time, and listen and watch current at every step. Stop immediately on abnormal noise or current; do not hope it will settle after a few minutes.
The point is to establish where the tool tip actually sits at Y=0. HMS-320MY has ±35 mm Y travel; HMS-550MY and HMS-550MYS have ±50 mm. Bring the tip to the workpiece centreline, record the machine coordinate as Y zero, then correct it with a test cut. Before any off-centre milling, confirm Y zero is written into the tool offset, or the first part will be out of tolerance.
A sub-spindle machine (HMS-550MYS) adds spindle spacing and mating: the site table lists 40–440 mm spindle spacing and 400 mm Z2 travel, so before mating check co-axiality, face cleanliness and equal clamping force. A tailstock machine (HMS-550MY) adds tailstock pressure and thrust: tailstock rail 460 mm, sleeve Φ80, MT5. Too much thrust distorts thin walls, too little causes chatter.
| Item | HMS-550MYS (sub-spindle) | HMS-550MY (tailstock) |
|---|---|---|
| Max bar | Φ52 (sub-spindle Φ46) | Φ52 |
| Main spindle | A2-6 / Φ65 / 4000 rpm / 8 inch | A2-6 / Φ65 / 4000 rpm / 8 inch |
| Sub-spindle / tailstock | A2-5 / Φ56 / 4000 rpm / 6 inch | Rail 460, MT5, sleeve Φ80 |
| Z2 axis | 400 mm | — |
| Spindle spacing | 40–440 mm | — |
Two to four hours in steps: raise spindle speed from 25% of rated to rated in stages of 15–20 minutes, index the turret more than 50 times, and run a full three-axis programme over the whole stroke. Record spindle temperature and noise every 30 minutes; abnormal temperature rise means lubrication or assembly needs checking first.
Choose a part that exposes three things at once: an OD, an off-centre bore or milled face, and a face. Thin walls expose clamping distortion; off-centre features expose Y zero errors. Do not use scrap for the test: the part must be measurable and repeatable, and the first-article data must be kept.
No. One good part proves the machine can make that part once; acceptance proves it repeats. Cut 5–10 consecutive parts and check scatter, then re-measure one part after four hours to see thermal effect. Record roundness, concentricity and position separately rather than only the OD size.
Five: leveling record, air and hydraulic pressure record, dry-run temperature and noise record, first-article and consecutive-part inspection report, and a parameter backup including tool offsets and macro programmes. The backup is the one most often skipped, and restoring parameters after a loss is measured in days.
Look at the axis and action named by the alarm, then at the conditions that action depends on: air pressure, hydraulic pressure, clamp-confirmed signal, door lock, turret position. About half of turn-mill alarms are unmet conditions rather than broken hardware. Note the alarm number, the action and the pressure value at the time before calling the supplier; it is far faster than saying “there is an alarm”.
Acceptance does not end when the form is signed; it ends when the first stable part comes off. Fix the six-step order and no operator will skip a step.